Czech Republic

We operate four ground-mounted solar plants in the Czech Republic. These plants were built in 2009 and 2010, during a time of strong market growth in the Czech Republic and have an installed capacity of 7.5 MW in total.

Hodonice

The solar park Hodonice is located in the Southern Czech Republic. A total of 10.848 solar modules are deployed across the plant. The subsidy mechanism was granted until the beginning of 2029.

2.1 MW
installed capacity

2.6 GWh
produced in 2020

2009
COD

c. 2,032t CO2
saved in 2020

  • Region: Liberec Capacity: 3.0 MW Status: Operational
  • Region: South Moravia Capacity: 2.1 MW Status: Operational
  • Region: South Bohemia Capacity: 1.2 MW Status: Operational
  • Region: South Moravia Capacity: 1.1 MW Status: Operational